Pre-Commissioning

Pre-commissioning covers the activities carried out during construction that prepare the unit to move into the main commissioning phase. Pre-commissioning activities include:

  • Filter installation
  • Installation of packing and internals in distillation columns
  • Catalyst loading in reactors
  • Verification of tests, inspections and non-destructive testing
  • Verification of hydrostatic tests
  • Cleaning of piping and equipment
  • Factory and site acceptance tests
  • Listing and follow-up of pending construction and instrumentation activities (punch list)
  • Control loop checks

Typical documents and activities in the Pre-Commissioning phase

  • Definition of operating systems
  • Procedures for flushing, blowing, chemical cleaning, equipment inspection (electrical, mechanical and instrumentation), final equipment closure, cold alignment and static tests of electrical equipment and instrumentation, among others
  • Lubricant verification and filling
  • Seal verification and filling
  • Protection settings
  • Punch list control
  • Operation and maintenance manuals
  • Blind list, terminal points and bolt torquing procedure
  • Commissioning and start-up sequence
  • Planning

This phase begins once most of the mechanical completion of the plant or systems has been achieved. It includes verification of conformity with design, verification of mechanical, electrical and instrumentation installations, cleaning of equipment and piping, and preliminary adjustments to equipment and systems.

Commissioning

During commissioning, the systems and equipment are put into initial operation for the first time. Dynamic checks of each element (electrical, instrumentation, piping and equipment) bring the facilities and their operating systems to the condition needed to start up, stabilize safely and smoothly, and reach the production and product yields they were designed for.

Examples of commissioning activities:

  • Inerting
  • Leak testing
  • Mechanical run tests of rotating equipment
  • Functional tests of equipment and systems
  • Functional tests of control loops
  • Protection settings
  • Energizing of electrical systems
  • Chemical loading
  • Operational tests

“Commissioning is the set of activities (tests) carried out with energy or process fluids to review and verify the integrity and proper operation of instruments, equipment and process systems, ensuring a successful start-up.”
Eng. Juan Mendez, ICG Commissioning