Year 2010
Thank you for reading this post, don't forget to subscribe!• Commissioning and startup of Star Project 7 of 7M BPD of fluids, Quifa Field, Meta.
• Commissioning and startup PAD-1 500 MBD of water, Quifa Field, Meta.
• Commissioning and startup of CPF Quifa SW Central Production facilities of 30,000 BPD Heavy Oil 13.5 ° API.
• Increase Capacity of Central Production Facilities in CPF-Quifa up to 45,000 BPD Heavy Oil 13.5 ° API.
Year 2013
• Commisioning and Startup of new surface facilities needed to achieve sustaining production capacity of 55,000 BPD field Quifa oil.
PLANT FACILITIES – CPF Quifa:
Commissioning and Startup in the Central Production Facility existing were executed:
• Third Free Water Knockout tank – FWKO 71,000 barrels of capacity, in conjunction with the Pumping System Free Water.
• Heat Exchanger No 2 Reconditioning to improve its thermal efficiency.
• Electrostatic Treater No. 9
PLANT FACILITIES – CPF Quifa:
• Third Skimmer tank SKIM, together with oil Pumping System and Water Pumping System for treatment.
• A (01) Water Treatment Plant. Induced Air Flotation Cell, No. 8 PTA capacity.
Injection:
• Commissioning and Startup of the pumping system of 650,000 BPD for treated water injection to wells of PAD No. 3 were excecuted
STAR PROJECT IN CAMPO QUIFA
• Activities of commissioning and Startup of new surface facilities needed to achieve sustaining production capacity of 20,000 BPD Field of fluid in the systems shown in the figure below
Comisionamiento Campo Quifa
Fecha: 2010 a 2013
Tipo Proyecto: Arranque y puesta en marcha de las facilidades centrales de producción y de sistema de inyección de agua de formación tratada a pozos
Áreas de acción: Precomisionamiento – Comisionamiento – Puesta en Marcha
Sector : Upstream / Producción
Cliente: Pacific Rubiales
Estatus: culminado